A company tied to Equinix has registered plans with the state for a $500 million, four-story data center at 1520 W. Mockingbird Lane near Dallas Love Field, across the street from a larger data center project it filed a year ago.
The project, called DA13, was registered with the Texas Department of Licensing and Regulation on Nov. 11, state records show. The filing describes a 372,443-square-foot new building, with construction scheduled to begin Feb. 1, 2027, and finish Dec. 7, 2029.
Beyond the shell, the listed scope includes 18 generators, seven generator pads and dunnage platforms, mechanical and electrical equipment, elevators and interior and exterior stairs. The filing lists the job as privately funded and built on private land. No tenant is named.
The owner of record is DA12 LLC, registered at One Lagoon Drive in Redwood City, California, the headquarters address Equinix lists in its federal securities filings. Margulies Hoelzli Architecture of New York is the design firm on the registration.
The project is at the earliest stage. Its status is listed as “project registered,” and no construction start has been recorded. Estimated costs and dates in state accessibility filings are preliminary and can change before work begins.
Second Equinix project on the same stretch
DA13 would sit opposite Equinix’s DA12 at 1550 W. Mockingbird Lane, on the former Taylor Publishing site. The same DA12 entity registered that project in two parts in November 2025.
The first registration, filed Nov. 19, 2025, covers a four-story, 372,517-square-foot data center estimated at $542.8 million, with 20 generators. It lists a Feb. 19, 2026, start and an Oct. 12, 2027, finish.
A second filing two days later covers a $293.7 million interior fit-out of the building’s first and second floors, about 158,293 square feet, set to run from Sept. 29, 2027, to March 30, 2028. State review of both DA12 registrations is complete.
Together the two DA12 filings total about $836.5 million. With DA13, Equinix-linked filings on the two Mockingbird Lane sites now add up to roughly $1.34 billion in estimated construction costs.
The DA13 site is a vacant tract that once held a 1970s-era office park. Equinix already operates eight data centers in the Dallas-Fort Worth area.
Why it matters
The filings point to a growing cluster of data center construction in the industrial area just south of Love Field, where older office and printing sites are being cleared for computing facilities. The 38 generators listed across DA12 and DA13 show how much backup power infrastructure such buildings carry.
Data center demand has been reshaping land use across DFW, from the Irving project approved on University of Dallas land to infill sites inside Dallas. Large projects like these typically work through state accessibility registration alongside city permitting, part of the broader path Dallas land development projects follow from site selection to construction.
Equinix had not publicly announced DA13 as of Nov. 27.